Mission Raftaar’ of Indian Railway Starts To Yield Results


Background:
  • Maximum speed of coaching trains has increased up to 130 kmph/160 kmph, but the average speed is hovering around 45 kmph. Maximum speed of freight trains has increased up to 75 kmph/100 kmph, but the average speed is hovering around 24 kmph.
  • Average coaching train speeds have declined by ~1 kmph in last 5 years. Average freight train speeds have declined by ~2 kmph in last 5 years.
Progress and Road Map:
  • A cross disciplinary, Mobility directorate has been set up in April 2016 to spearhead the mission.
  • For a focused action, Golden Quadrilateral routes along with diagonals (Delhi – Mumbai, Delhi – Howrah, Howrah- Chennai, Chennai – Mumbai, Delhi – Chennai and Howrah – Mumbai) have been taken up for initial emphasis. These are the principal routes of the railways as they carry 58% of freight traffic and 52% of coaching traffic with a share of only 15% of the network.
  • Multi-pronged strategy has been developed to overcome the existing impediments due to fixed infrastructure, movable infrastructure, operational practices and institutional mechanisms.
Thrust of the strategy:
  • To move in the direction in which these routes are developed in a unified way making them seamless and free from congestion points. So far such development works have been largely guided and governed by needs of individual division/ zone due to which the works were dispersed/ distributed/ discontinuous and speed gain commensurate to the inputs could not be realized.
  • To establish operating systems in which the trains technically have the best capability to achieve maximum possible speed in least time along with quickest acceleration and deceleration capability so that the transit time is reduced.
Action Taken:
  • Replacement of loco hauled commuter trains with MEMU/DEMU trains: MEMU trains have a potential for average speed increment of up to 20 kmph in comparison to loco driven passenger trains. Recently, the busiest Ghaziabad- Allahabad – Mughalsarai route has been made free from conventional trains by replacement by MEMU. The punctuality of this route has shown significant improvement.
Target is to do replacement on all routes. We require 1048 MEMU coaches and 136 DEMU coaches to implement this on these six routes. To achieve this target in three years, action plan has been drawn out to ramp up the production of MEMU to 400-500 per annum in next three years as against the present level 190 per year at present.
  • Introduction of Twin Pipe Air Brake System on freight trains: Twin piped braking system saves on an average ~90 seconds in every event of braking. Hence over a long distance this feature in the trains has a big potential for reducing the transit time and accelerating average speed. Board has decided that all new freight stock will have twin pipe system and the existing stock will be retrofitted with twin pipe. About 2lac wagons have to be retrofitted. 7000 will be done in the current year. Approval for another 20000 has been done, which is under process of sanction. In the budget 2017-18 sanction for another 60000 wagons will be planned. Effort will be made to achieve the target by accelerating the progress.
  • Right Powering of freight trains: Ratio of Horsepower of the locomotive to the trailing load of the train. (HP/TL ratio). Appropriate HP/TL ratio saves about 10 to 12 minutes in the time taken to attain the maximum speed level. Internationally this ratio is between 2-2.25. On Indian Railways, due to increase in trailing load from 2400 ton/3200 ton in year 1970 to 5308 ton in year 2016, HP/TL ratio has dropped from a level of 1-1.30 to a level of 0.94-1.13 over the same period. Board has decided to implement a powering arrangement for freight trains with a ratio of 1.5-2.0. Action plan is being finalized for achieving the implementation in next three years.
  • Review of time table:
    • To avoid traction change and loco reversals at busy stations/ terminals.
    • Increase time tabled average speed by eliminating slacks and taking into account speed increases which have taken place on the section
  • Review of coaching trains and freight stocks running at less than maximum permissible speedsRemoval of constraints in the fixed infrastructure on these routes is considered a high priority. These routes are having about 9100 route kilometres. Major impediments have been identified and following areas have been finalized for focused action.Raising of Sectional Speed to minimum 130 kmph: Out of 9100 route km, 6400 km (~70%) is having sectional speed of less than 130 kmph.
  • Removal of Level Crossings: There are 2736 level crossings on 9100 route km averaging one LC every 3-4 km. 931 are already sanctioned for elimination.
  • Removal of Speed Restrictions: On these routes, there are speed restrictions at about 730 locations existing since long due to various factors pertaining to design and maintenance of fixed assets. There is a restriction every 15 km on these routes.
  • Raising of Speeds on Turnouts: At present ~10% turnouts on these routes have a speed of less than 30 kmph and all are less than 50kmph.
Strategy and institutional mechanism for implementation:
We have decided for a paradigm shift in approach to works. Route to be the primary unit for decision about works as against existing practice of zonal/ divisional jurisdiction. This fundamental shift will prove to be a game changer for achieving unified development of the routes essential for achieving Mission Raftaar goals.
Key Elements of the decision:
  • Planning and Sanction of Works: Only one work for each route clubbing all activities. Works to be planned centrally.
  • Financing: Works to be financed through EBR-IF as there is high likelihood of favourable ROR on the route basis.
  • Execution: Route wise execution. The work of each route to be entrusted to one execution authority for accountability and expeditious execution by deploying state-of-the-art engineering technology/machines. There is a big role of technology in saving the execution time and minimizing the requirement of interruption to train flow in traffic block. This is very important because chosen routes are very busy hence the objective will be to cause minimum inconvenience to the passengers and setback to operations. A Traffic Block Optimization System on an IT platform is being developed to provide a congenial environment for execution of works required to achieve mission goals.

Comments

Popular posts from this blog

Sansad adarsh gram yojna: Chikhli village get new looks and developments in gujarat

Chandrakant Raghunath Patil, MP from Navsari, adopted Chikhli.  Chikhli seen improvement in Sanitation and road renovation under SAGY. The infrastructure is improved.It is emerging as the template of village development. Patil completed the task in just three months. 380 toilets were built in Chikhli, many of them in the two slums  life has become better after construction of toilet in their houses  regular affair during the monsoons. A huge Shiva statue built six years ago by an NRI on the river bank had lost its colour and texture. The MP built a protection wall all along the riverbank and renovated a temple and the Shiva idol. renovation of road circles in a public-private partnership  putting waste collection bins around the village, procurement of a diagnosis machine for the Rotary Eye Hospital (in the nearby Navsari), a library in the village panchayat office, gas-based cremation at the village crematorium, a modern aganwadi centre and a bus stop.

Hundred villages of Jharkhand has been selected under Pradhan Mantri Adarsh Gram Yojana

The Central Government has selected 100 villages of Jharkhand under Pradhan Mantri Adarsh Gram Yojana. These villages will be equipped with all fundamental facilities. Chief Minister Mr. Raghubar Das said that villages having more than 50% Schedule Tribe population will be considered for this. The Central Government is giving 20 lac for thwe development & the additional 20 lac will be given by the State Government. 36 villages from Chatra, 22 from Palamu, 18 from Deoghar,14 from Hazaribag & 10 from Giridih district have been identified for Pradhan Mantri Adarsh Gram Yojana.    1 view  •  Written 1m ago Upvotes 0 Comment Share

PORTAL FOR PUBLIC GRIEVANCES Grievance Redress Mechanism in Government ::

While media is busy praising Anti Corruption Helpline number of Delhi (It is a nice step if it works). GOI has developed a special portal for public grievance (visit  www.pgportal.gov.in  ). Now register your complaint for any government department online to get it solved.